PROJECT PROGRESS
The project, at a glance

Website first. Relationships at the center.

Discovery is complete. The 1B canonical database foundation is deployed and verified; engineering handoff is complete. Follow website foundation delivery and the revised roadmap separately.

Current foundation: 1A is 100% complete. 1C is 8/10 deliverables (80%); payment sandbox and integrated checkout/operating/compliance review remain. The 90% combined figure refers only to these twenty foundation stories, not the whole project.
November 9 direction: Website VIC prices and future-wine preorders replace relevant app functions. The private invitation-only community stays. Permanent House reservations are no longer assumed; future event booking is conditional. One unified marketing store replaces separate regional marketing stores. These new functions are planned, not implemented. Website member work ↗
Ready for Gigi and Jasmine: Brand context, Journal/product journey, four-wine mood direction, content priorities and practical image specifications are prepared. Johnathan still needs to deliver the brief and arrange Gigi’s project access. Content brief ↗ · Meeting follow-ups ↗
November 23 database delivery: 1B is 100% complete (8 of 8 verified deliverables), with eight migrations and fifteen secured tables deployed. Canonical UIDs, identity mapping, consent/membership records, wine/vintage/case references and event deduplication are implemented; 28 core tests and verified hosted/native/access checks pass. See completed work and remaining 1B gates. Website synchronization follows under 1D; payment receipt and milestone acceptance remain separate.

Current milestone delivery.

Active sprint: Milestone 1A – 1C · Jira board 1
1A discovery complete
Earlier discovery record · October 20

The foundations for delivery tracking are in place.

  • New D10 compliance-provider response read in full. Twelve client-supplied discovery sources now indexed; D11/D12 wine briefs received; prior Word text and House fingerprint unchanged.
  • Jasmine approved the brand brief and accepted the refined personas for 1A. Both stories are now complete.
  • All ten 1A deliverables are complete. Johnathan revised the compliance discovery criterion to the delivered matrix/handoff. Jasmine’s original comments remain preserved; final milestone sign-off is separate.
  • Four homepage, four post and four product mockups sent to the client for review, confirmed by Johnathan. Jasmine selected Homepage Layout 03 + Publication Post 03 + Georgia Italic headlines. Black-and-white editorial imagery and the original-logo comparison are live. The WordPress foundation is delivered at lumist.wine; BuddyPress initial setup is complete, with broader integration privacy checks pending.
Current delivery progress

All ten 1A discovery deliverables are complete. Product and compliance discovery are delivered. Final counsel validation is a pre-live-sales requirement. 1C implementation continues separately.

No entire milestone is recorded as accepted. Future milestone progress is unmeasured.

1B database foundation · 100% complete

Engineering delivery complete · formal company acceptance separate
Open SCRUM-33

Delivered: eight migrations, fifteen secured business tables and a separate metadata/change journal; canonical identity/source mappings, consent/membership history, wine/vintage/case models, event contracts and reviewed merges.

Verified: 28 core tests, 8 native CI groups, 8 hosted concurrency/recovery groups and 14 actual-login/context checks pass. Private source and exact-commit CI are verified; a fresh remote checkout passes. Four wine/case references remain planning stock, with zero people/orders or synthetic business fixtures.

Agent context: all 430 hosted objects have purpose descriptions, including every one of the 136 business columns. Agents can inspect the object catalog, seven operating rules and append-only change history. Unannotated business writes from the named writer are rejected; approved writes retain transaction/object/actor context without customer payloads.

Writer rule: Johnathan is the sole authorized human writer. Everyone else is read-only unless he expressly authorizes otherwise. Shawn remains organization Owner by explicit exception; privileged ownership is distinct from routine write authorization.

Private source and agent guide · Verified CI · Implementation record

8 of 8 engineering deliverables complete. Formal company acceptance and payment remain separate. Actual website synchronization is 1D. Physical/PITR/platform recovery and operating retention/recovery targets remain documented operational follow-ups.

What will move the project forward.

Suggested contacts below are input sources, not assigned Jira owners.
Johnathan → Gigi / Jasmine

Deliver the content handoff

Send the prepared context/materials brief. Invite Gigi once her work email and permissions are confirmed. Place the first in-house story and original photographs; no extra discovery workshop.

Content handoff ↗
Johnathan → Eazon

Review the revised scope

Remove the native app packages, retain bounded website member/preorder functions and submit the revised commercial proposal. Existing 1B/1D invoices concern retained database/integration work.

Scope review ↗
Eazon / agency → Johnathan

Provide sandbox and operating feedback

Sandbox access unblocks payment tests. Working-site compliance/operating feedback unblocks integrated checkout review. Written Stripe wine approval and actual shipping permissions remain separate live-sales gates.

Sandbox work ↗
Learning, not overdue: mature VIC scoring/customer-fit intelligence, later master synthesis and exact editorial cadence can evolve. Optional photography and future event booking are not silently added to current completion requirements.

The work behind each milestone.

Expand any item for checkpoints, requirements, remaining work and source documents.
How the percentages are calculated

Delivery completion = Jira Done deliverables ÷ tracked deliverables × 100. Each deliverable counts once. SCRUM-8, SCRUM-9, SCRUM-10, SCRUM-11, SCRUM-12, SCRUM-13, SCRUM-14, SCRUM-15, SCRUM-16 and SCRUM-17 are Done: 10/10 for 1A (100%) and 18/20 across current 1A + 1C scope (90%), including eight delivered 1C foundations. Learning and later implementation dependencies do not reduce 1A completion. This is a count of finished deliverables, not an estimate of hours or the whole future project.

Documentation coverage = captured checkpoints ÷ applicable checkpoints × 100. Partial checkpoints remain visible but receive no invented fractional credit. Missing checkpoints receive no credit. Learning-phase checkpoints are excluded from the denominator. This reference inventory also tracks downstream setup and operating details; an outstanding inventory row is not automatically a 1A completion requirement. Counts are equal checkpoint counts, not equal-effort estimates.

A checkpoint shows 100% when its documentation is Captured, 0% when Missing, and “Partial” when no reliable fraction is supplied. Milestone bars roll up their checkpoints, not averages of rounded item percentages. Jira Done counts and formal acceptance remain separate. A documented requirement does not mean implemented software.

The full project roadmap.

Four phases · sixteen milestones · November website-first direction; commercial revision pending client approval

The roadmap includes the November website-first revision. Replacement package scope/fees remain proposed until accepted. 1B is 100% complete based on eight of eight verified deliverables; other future milestone progress remains unmeasured; three new member-experience stories and one content handoff task are tracked outside the twenty-story foundation denominator. No calendar delivery date, payment or formal acceptance is inferred from the proposal. Sprint end: October 16, 2026; this is a planning date, not an acceptance deadline.

Requirements, kept traceable.

64 source-backed entries, with proposed milestone routing and decision state.
Full requirements register ↗
Sources, freshness and evidence limits

Jira supplies workflow status, owners and story requirements. Confluence supplies documented input checkpoints and remaining asks. The local master memory supplies the 16-milestone proposal map. This page is a published snapshot, refreshed as project work is recorded; it does not continuously poll Jira.

1A progress notes · 1C progress notes · Source register · Decisions & open questions

October 20: all 22 milestone epic/story records were retrieved; the 20 child stories are the dashboard’s delivery scope. Two Jira sample tasks are excluded. Current status, summary, description, parent, assignee, labels, priority and update date were checked. Full comment/reaction audit remains dated October 15; this refresh does not claim a new full activity audit. Input-review contacts are documented separately from actual Jira assignees, which remain unassigned. No assignee capacity, software deployment, executed test, reviewed milestone criteria, contract, payment or acceptance record is inferred.

Search indexing is discouraged through noindex / nofollow directives. Linked Jira and Confluence records retain their own access requirements.