PROJECT PROGRESS
The project, at a glance

One clear view of what’s next.

Discovery is taking shape. The website foundation is being specified. Follow the current work, what we’ve captured, and what still needs a decision.

How to read progress: delivery progress counts completed Jira deliverables. Documentation coverage tracks captured, partial and missing inputs separately. A completed deliverable counts toward its milestone; it does not mean the whole milestone is accepted.

Two workstreams, moving together.

Active sprint: Milestone 1A – 1C · Jira board 1
Discovery & preparation underway
Recorded this morning · October 13

The foundations for delivery tracking are in place.

  • All three discovery source documents reviewed and indexed.
  • Ten 1A discovery drafts, two milestone hubs, and two rolling progress notes populated in Confluence.
  • Twenty deliverable stories organized in the active Jira sprint, with progress and evidence links reconciled.
  • Project progress dashboard completed and confirmed by Johnathan; live at lumistproject.info.
Current delivery progress

The project progress dashboard is complete. The remaining discovery and foundation deliverables continue through their Jira workflows.

No entire milestone is recorded as accepted. Future milestone progress is unmeasured.

What will move the project forward.

Suggested contacts below are input sources, not assigned Jira owners.
Brand & experience · Jasmine

Assets and website decisions

Collect current logo, fonts, approved photos and factual story sources. Confirm Journal / House / Contact structure, launch languages, account fields and customer-facing states.

Brand discovery · SCRUM-11 ↗
Commerce & operations · Shawn / operators

Real product and policy inputs

Supply the launch wine / vintage / SKU file, prices, stock units and source. Confirm membership activation, reservations, cancellations, refunds and restocking rules.

Product discovery · SCRUM-12 ↗
Launch dependency · Counsel / operators

Compliance and provider decisions

Obtain a sourced jurisdiction and permit matrix, age / tax / shipping requirements, fulfillment contacts and alcohol merchant eligibility before live commerce configuration.

Compliance inputs · SCRUM-17 ↗
Intentionally left open: the later master intelligence database, customer-fit model, scoring and promotion rules are in a learning phase. They do not block completion of 1A.

The work behind each milestone.

Expand any item for checkpoints, requirements, remaining work and source documents.
How the percentages are calculated

Delivery completion = Jira Done deliverables ÷ tracked deliverables × 100. Each deliverable counts once. SCRUM-8 contributes one complete deliverable: 1/10 for 1A (10%) and 1/20 across the current 1A + 1C scope (5%). This is a count of finished deliverables, not an estimate of hours or the whole future project.

Documentation coverage = captured checkpoints ÷ applicable checkpoints × 100. Partial checkpoints remain visible but receive no invented fractional credit. Missing checkpoints receive no credit. Learning-phase checkpoints are excluded from the denominator. Counts are equal checkpoint counts, not equal-effort estimates.

A checkpoint shows 100% when its documentation is Captured, 0% when Missing, and “Partial” when no reliable fraction is supplied. Milestone bars roll up their checkpoints, not averages of rounded item percentages. Jira Done counts and formal acceptance remain separate. A documented requirement does not mean implemented software.

The full project roadmap.

Four phases · sixteen milestones · September proposal baseline

Future milestone deliverables are known scope; progress percentages remain unmeasured until Jira work and evidence checkpoints are defined. No calendar delivery date, payment or formal acceptance is inferred from the proposal. Sprint end: October 16, 2026; this is a planning date, not an acceptance deadline.

Requirements, kept traceable.

37 source-backed entries, with proposed milestone routing and decision state.
Full requirements register ↗
Sources, freshness and evidence limits

Jira supplies workflow status, owners and story requirements. Confluence supplies documented input checkpoints and remaining asks. The local master memory supplies the 16-milestone proposal map. This page is a published snapshot, refreshed as project work is recorded; it does not continuously poll Jira.

1A progress notes · 1C progress notes · Source register · Decisions & open questions

All 22 milestone epic/story records were retrieved; the 20 child stories are the dashboard’s delivery scope. Two Jira sample tasks are excluded. Status, summary, description, parent, assignee, labels, priority and update date were checked. Every current story is unassigned. No assignee capacity, software deployment, executed test, reviewed milestone criteria, contract, payment or acceptance record is inferred.

Search indexing is discouraged through noindex / nofollow directives. Linked Jira and Confluence records retain their own access requirements.